Program progress by epic against the original plan — agent-refreshed register with an append-only deviations log (REQ-012, ADR-009).
Epic board — progress vs the original plan
One row per epic: the roadmap’s 13 phases (P0–P12) plus the pre-program commercial phase. The Baseline column is frozen (it mirrors the roadmap and only changes with a formal re-baseline); everything else is maintained by the board-refresh agent — nightly and on demand — from the HANDOFF, session logs, and the vault (ADR-009). M1 ≈ September 2026 (assumption, pending kickoff confirmation).
Status legend: not-started · in-progress · on-track · at-risk · done.
Epics
| Epic | Track | Baseline | Status | Progress | Latest |
|---|---|---|---|---|---|
| PRE — Commercial & kickoff | Foundations | pre-M1 (Jul–Aug 2026) | in-progress | 70% | Stage-1 offer drafted, priced and discounted; awaiting TPL C-suite review, then issue to Prime Products |
| P0 — Preparation & governance | Foundations | M1 | in-progress | 20% | Charter, governance model and board outline drafted; CEO sign-off pending |
| P1 — Discovery & requirements | Foundations | M1–M3 | in-progress | 20% | Method + 5 questionnaires ready; REQ-001…014 captured; pilot clarification call held (cylinders dept) validates the interview approach — general department discovery not yet started |
| P2 — Process map & AI opportunities | Foundations | M2–M4 | not-started | 0% | Method defined in discovery framework; waiting on discovery |
| P3 — Infra architecture | Platform | M2–M3 | in-progress | 10% | Technical blueprint drafted (assumption-flagged); site survey pending |
| P4 — Hardware procure & deploy | Platform | M3–M6 | not-started | 0% | Gated by board budget approval (target end M2) and HQ server-room survey |
| P5 — LLM stack implementation | Platform | M4–M7 | not-started | 0% | Stack chosen in blueprint (vLLM, Qdrant, n8n; Llama-3.3-70B + Krikri-8B) |
| P6 — Obsidian KB design & rollout | Knowledge & Visibility | M2–M9 | in-progress | 15% | Vault live with conventions and program docs; raw-source layer + automated ingest pipeline shipped (ADR-012/013); first Prime Products department profile captured (cylinders) |
| P7 — Mission Control site | Knowledge & Visibility | M1–M12 | on-track | 50% | Live ahead of baseline at vanos.tpl.one behind Access — nav regrouped into dropdowns as page count grows; still doubles as the pilot’s working dashboard, plus docs, graph (growth-replay timeline), tasks, wiki-chat, board |
| P8 — Department pilots | Value Delivery | M6–M8 | in-progress | 25% | Pilot offer priced, pending TPL C-suite review; first sample order-email batch (6 of 20–50) received and fully distilled, revealing the four-tier order-brokerage chain and a hard mailbox-ingestion constraint — still awaiting the team-details handoff and remaining sample volume |
| P9 — Agents & automation | Value Delivery | M7–M10 | not-started | 0% | Use-case pipeline + agent registry drafted |
| P10 — Training & change mgmt | Value Delivery | M4–M11 | not-started | 0% | Change/training plan drafted |
| P11 — Full rollout | Value Delivery | M9–M11 | not-started | 0% | — |
| P12 — Optimization & governance | Value Delivery | M11–M12 | not-started | 0% | — |
Deviations from baseline
Dated, append-only. Only real changes against the original plan (scope, timing, cost) — not routine progress.
- 2026-07-03 — Cost (PRE): Stage-1 fixed fee changed €69,500 → €59,075 (15% program-launch discount), payment split 40/60. Source: offer TPL-PRIME-2026-001.
- 2026-07-03 — Scope (P7): Wiki-chat added — conversational access to the knowledge base on the Mission Control site (REQ-011/ADR-008: Bedrock Opus 4.6, no retrieval DB, OKD-hosted). Not in the original WBS; delivered same day.
- 2026-07-03 — Timing (P7): Mission Control delivered ahead of baseline — v1 live pre-M1 (baseline had v0 launching in M1).
- 2026-07-02 — Timing (P6): Knowledge-base vault bootstrapped pre-M1 (baseline start M2) — program docs already live in it.
- 2026-07-03 — Assumption (all): program start month still unconfirmed — M1 ≈ September 2026 pending CEO sign-off; all calendar dates shift with it.
- 2026-07-06 — Timing (P8): Pilot work started pre-M1 — department selected (cylinders/email-order desk), REQ-014 captured and validated, and the CEO clarification call held and ingested. Baseline had pilot department selection at M4 and pilots launching M6–M8.
- 2026-07-06 — Scope (P6): Raw source layer (
raw/) and an automated ingest pipeline added (ADR-012/013) — source material (e.g. call transcripts) is committed for provenance and auto-distilled into the wiki via a detect → distill → PR flow. Not in the original WBS. - 2026-07-11 — Cost (P8): First pilot wave priced — €51,000 fixed fee (15% program-launch discount applied), payment split by phase. Baseline Stage 7 pricing was an unset placeholder. Source: offer TPL-PRIME-2026-002.
- 2026-07-15 — Assumption (P8): First sample order-email batch (6 of 20–50 requested) received and fully distilled — reveals Prime’s order-entry process as a four-tier email brokerage chain (customer/shipowner-manager → Prime → manufacturer → port agent) with two deterministic quote↔order match keys, but confirms a hard technical constraint: the M365 search connector cannot expose nested email-attachment content, so automated mailbox ingestion needs full Graph API attachment access (or IMAP/EWS) plus PDF/OCR extraction, not the connector path originally assumed. Source: discovery note.